The Company’s performance in the year 2024, The revenue from services increased of 486.43 million baht or 87.68% compared with the year 2023. The Company has the following analysis on its results of total revenue, cost and expenses.

Revenue

The Company had Ship Repairing revenue was 482.54 million baht, a decrease of 11.16 million baht or 2.26% from the year 2023. This was because the company's customers are mainly private vessels, whose repair value is not as high as that of government vessels. In the fourth quarter of 2024, the Samut Prakan branch undertook improvements by dredging the waterway in front of the pier to maintain the required depth of the waterway according to the size of the vessels using the company's services. This resulted in an impact on the volume of ship repair work in the fourth quarter of 2024. However, the performance in the year 2024 for ship repairs still met the set targets. The main drivers of the performance came from the oil tanker and ferry & passenger ship, in line with economic growth, supported by the tourism sector benefiting from foreign tourists. Additionally, the increase in global trade volume contributed to the growth of the shipbuilding and ship repair industries. The Surat Thani branch saw increased revenue due to high-value yacht repair projects.

Shipbuilding revenue was 503.09 million baht, which increased 482.33 million baht or 2,323.36 % compared with the year 2023. The company recognized revenue of the Project Hydrographic survey & Buoy Tender from Royal Thai Navy which had accumulated revenue recognition of 61.08% and the Project Single Conveyor Garbage Collection Boat (HDPE) from Royal Thai Navy which had accumulated revenue recognition of 21.15%. This had a higher value Compared to the year 2023 when The Project Tugboat from Royal Thai Navy revenue was recognized 16.63 million baht, was recognized from the delivery in August 2023, with most of the revenue recognized in 2022 and the Project Hydrographic survey & Buoy Tender from Royal Thai Navy revenue was recognized 4.13 million baht which had accumulated revenue recognition of 0.50%.

Ship Supply revenue was 4.10 million baht, which decreased 4.77 million baht or 53.78% compared with the year 2023. This revenue is from the sale of single conveyor trash collector Boat (HDPE) project to Precious Shipping Public Company Limited amount 1 vessel. The vessel will be used for garbage collection in the canals of Bangkok. The company received the project through its subsidiary, Eco Marine Co., Ltd., and the vessel was delivered on November 19, 2024, at Prem Prachakorn Canal, Bangkok.

Cost and Expenses

The gross profit of 206.37 million baht for the year 2024, an increase of 60.10 million baht or 41.09% compared to the year 2023. Profitability has decreased, with the gross profit margin of 19.82% which decreased 26.37% in the year 2023. The decrease is partly due to relatively high shipbuilding costs.

The cost of services amounted to 834.86 million baht, an increase of 426.33 million baht or 104.36% compared to the year 2023. The cost of services increased in line with the rise in revenue and the higher prices of labor, materials compared to the year 2023. Additionally, in the year 2024, the proportion of recognized revenue and project costs for shipbuilding is higher than the year 2023, as high-value large machinery and equipment items for shipbuilding were purchased. Additionally, because the cost of shipbuilding is higher than the cost of ship repairs, the overall cost has increased.

The distribution costs amounted to 9.73 million baht, an increase of 1.99 million baht or 25.71%. Administrative expenses and Management remuneration amounted to 141.21 million baht, an increase of 18.29 million baht or 14.88% compared to the year 2023. This is due to employee-related expenses and welfare were paid according to the company's performance. Additionally, there was an increase in depreciation and amortization resulting from investments in equipment and tools that enhanced the company's operational efficiency.

The Finance costs amounted to 5.08 million baht, a decrease of 5.87 million baht or 53.61%. The company’s short-term loans and long-term loans from financial institutions have decreased. Additionally, financial institutions lowered their interest rates, resulting in a reduction in the company's interest payments.

Operating Results & Financial Condition

Operating Results & Profitability

The gross profit of 206.37 million baht for the year 2024, an increase of 60.10 million baht or 41.09% compared to the year 2023. Profitability has decreased, with the gross profit margin of 19.82% which decreased 26.37% in the year 2023. The decrease is partly due to relatively high shipbuilding costs, In 2024, costs related to the ship's structural work and the large machinery systems, which have high values. However, the company was able to manage risks and control costs, keeping them within the budgeted.

Liquidity & Capital Adequacy

Liquidity Analysis

The current ratio as of December 31, 2024, was 1.03 times, an increase from 0.96 times on December 31, 2023. This improvement was due to a 135.38 million baht increase in current assets, primarily from trade receivables, other current receivables, and unbilled revenue. On the liabilities side, current liabilities increased by 109.07 million baht, primarily from short-term loans (trust receipts payable) and trade payables. In 2024, the company experienced improved liquidity compared to 2023.

The gross profit margin for 2024 was 19.82%, a decrease of 6.54% compared to the previous year. Despite an 87.68% increase in revenue from contracts, the company faced higher raw material costs and labor costs. Furthermore, part of the decrease was due to the relatively high cost of shipbuiding, as 2024 saw the recognition of costs related to the vessel hull structure and major machinery systems, which were high-value items. However, the company was able to manage risks and control costs within the budget, resulting in a lower gross profit margin compared to the previous year

• Cash flow from operating activities for 2024 amounted to 37.03 million baht, a decrease of 327.24 million baht compared to 2023. The main factors contributing to the decrease in cash flow were the increase in unbilled revenue from completed work not yet collected and an increase in trade receivables, which led to a reduction in cash.

• Cash flow from investing activities was 46.82 million baht, an increase of 13.76 million baht. This was due to the fact that in 2024, there were no significant asset purchases, only improvements to the floating dock, which is an asset enhancement aimed at supporting and improving operational efficiency.

• Cash flow from financing activities was 46.30 million baht, an increase of 198.08 million baht compared to 2023. This increase was primarily due to a rise of 90.68 million baht in trust receipts payable. In 2024, the Hydrographic survey Buoy Tender vessel project of the Royal Thai Navy progressed to 61.08%, leading to the purchase of high-value machinery and equipment, resulting in the company utilizing more trust receipt financing from the bank.

Cash Flow Analysis

As of December 31, 2024, cash and cash equivalents amounted to 68.30 million baht, a decrease of 37.86 million baht from 2023.

Which consists of:

Net cash from (used in) operating activities (37.03) million baht

Net cash from (used in) investing activities (46.82) million baht

Net cash from (used in) financing activities 46.30 million baht

Unrealized foreign exchange gain (loss) (0.30) million baht

Net increase (decrease) in cash (37.55) million baht

As of December 31, 2024, the debt-to-equity ratio was 1.09 times, an increase from 0.93 times in 2023. This was due to an increase in liabilities by 103.28 million baht, mainly from short-term borrowings from financial institutions (trust receipts payable), while equity increased by only 30.42 million baht. The increase in equity was attributed to a net profit of 50.88 million baht in 2024 and a dividend payment of 20.66 million baht from the 2023 operating results.

The profitability ratio improved compared to 2023, with the net profit margin increasing to 4.82 times, up from 3.06 times. The interest coverage ratio was 25.12 times, an increase from 7.82 times. This improvement was primarily due to a net profit increase of 33.37 million baht, while long-term borrowings from financial institutions decreased by 11.76 million baht, or 66.22%. The reduction in long-term borrowings was a result of the company’s timely principal repayment, leading to a reduction in financial costs by 5.87 million baht, or 53.63%, compared to the previous year.

The debt repayment capacity ratio was 7.80 times, an increase from 3.85 times, due to the company’s ability to repay long-term debts as scheduled and partially repay short-term borrowings, which led to a reduction in short-term borrowings by 5.00 million baht. In addition, EBITDA increased by 41.92 million baht. The company also complied with key loan agreement conditions, including restrictions on the use of loan proceeds for purposes other than those specified in the contract, prohibitions on transferring, selling, leasing, disposing of, or encumbering assets, and not incurring any debt or liabilities through loans or guarantees that would cause the total debt-to-equity ratio to exceed 1.3:1 or fall below 0. The company agreed to maintain a debt service coverage ratio of no less than 1.5 times.

Sources of Funds

In 2024, the company had total liabilities of 502.77 million baht, an increase of 103.28 million baht, consisting of current liabilities of 440.82 million baht and non-current liabilities of 61.95 million baht. The increase in current liabilities was primarily due to an increase in trust receipts payable by 90.68 million baht and trade payables by 141.45 million baht. This increase was driven by the progress of the Royal Thai Navy’s Hydrographic survey Buoy Tender vessel project, which reached 61.08%, leading to the purchase of high-value machinery and equipment. Non-current liabilities decreased by 5.79 million baht due to a reduction in long-term borrowings from banks.

Stockholders’ equity consists of paid-up capital of 258.29 million baht, and appropriated retained earnings of 25.83 million baht. In 2024, no additional legal reserves were allocated as the company had already set aside the required reserves in accordance with the law. Unappropriated retained earnings amounted to 175.66 million baht, an increase due to net profit of 50.88 million baht for the year and dividend payments of 20.66 million baht from the 2023 operating results.

The Return on Assets (ROA) was 5.67, an increase from 2.13 in 2023. The company had an increase in assets of 133.70 million baht and a profit increase of 33.30 million baht. The assets contributed to an increase in revenue compared to 2023, as the increase in assets was mainly due to unbilled revenue (for work already delivered or completed but pending payment from customers) and other current receivables (prepaid expenses).

Asset Management Capability

Asset Analysis

The company’s total assets are reported at 964.35 million baht, an increase of 133.70 million baht or 16.10%. Current assets increased by 135.38 million baht or 42.40%, while non-current assets decreased by 1.67 million baht or 0.33%. Key details are as follows:

• Cash and cash equivalents decreased by 37.86 million baht or 35.66%. In 2024, part of the cash was used to repay short-term loans from financial institutions. In addition, the Hydrographic survey Buoy Tender vessel project for the Royal Thai Navy progressed to 61.08%, leading to significant payments for materials and equipment. Moreover, dividend payments for the 2023 operating results amounted to 20.66 million baht, resulting in the reduction of cash.

• Trade and other current receivables increased by 21.32 million baht, or 101.91%. Most of the increase came from other current receivables (prepaid expenses), which were recorded for dredging expenses at the port, scheduled for the fourth quarter of 2024.

• Advance payment for purchase of goods decreased by 35.49 million baht or 40.39%, as most of the advance payments for equipment related to the Hydrographic survey Buoy Tender vessel project for the Royal Thai Navy had already been made by the end of 2023.

• Unbilled revenue increased by 191.86 million baht or 260.08%, primarily driven by an increase of 163.41 million baht from ship building and 25.17 million baht from ship repair projects. The majority of these amounts relate to completed work that has not yet reached the billing due date.

• Inventory decreased by 0.29 million baht or 1.43%, primarily due to significant progress in the hull construction ofthe Hydrographic survey Buoy Tender vessel project toward the end of the year. In addition, major machinery and critical equipment installations progressed, leading to the rapid issuance and utilization of ordered materials.

• Restricted bank deposits decreased by 6.00 million baht or 100% as the company successfully released the collateral requirement for bank guarantees issued for overseas project bidding.

• Property, plant, and equipment decreased by 3.52 million baht or 0.91%. In 2024, the company did not invest in high-value assets during the year, except for the improvement of a floating dock. This asset enhancement was undertaken to support and improve operational efficiency.

Other Analysis

TitleDescription
Debt and Equity

Liabilities Analysis

The company’s total liabilities are reported at 502.77 million baht, an increase of 103.28 million baht or 25.85%. Key details are as follows:

• Bank overdrafts and short - term loans from financial institutions increased by 85.68 million baht or 68.54%. While short-term borrowings from financial institutions decreased by 5.00 million baht, trust receipts payable increased by 90.68 million baht. This was due to the Hydrographic survey Buoy Tender vessel project for the Royal Thai Navy progressing to 61.08% in 2024, leading to significant purchases of high-value machinery and equipment. As a result, the company utilized trust receipt financing from the bank.

• Trade payables and other current payables increased by 141.45 million baht or 428.25%, primarily due to payables arising from the purchase of materials and equipment for the hydrographic operations vessel construction project, both domestically and internationally.

• Long-term borrowings from banks decreased by 11.76 million baht or 66.22% due to scheduled principal repayments.


Shareholders' Equity Analysis

Shareholders’ equity amounted to 461.58 million baht, an increase of 30.42 million baht or 7.06% from 2023. This was due to an increase in the total comprehensive income of 33.30 million baht and a dividend payment of 20.66 million baht was made from the 2023 performance.

Revenue Recognition Policy and Accounts Receivable Quality Analysis

Revenue recognition policy and Trade and other current Receivables analysis

The company has the revenue recognition following :

• The Company recognizes revenue from the provision of services under the contract. according to the ratio of work completed which surveys and evaluates the work done by the company's engineers. The Company will set aside provision for losses for the shipbuilding project and ship repairs in full. When it is clear that the project will suffer a loss.

• The recognised revenue which is not yet due per the contracts has been presented as “Unbilled complete construction in progress” in the statement of financial position

• The obligation to transfer service to a customer for which the subsidiaries have consideration or an amount of consideration is due from the customer is presented as “Advance received from customers” in the statement of financial position. Deferred income will be recognised as revenue when the Group has completely performed the obligation stated in the contract

• Interest income is recognised on an accrued basis, based on the effective rate method.

• Other income is recognised on an accrual basis.


Trade and other current Receivables analysis

The company will set up an allowance for doubtful accounts. Estimated the amount that may occur from the collection of uncollectible debtors. This reserve amount is estimated based on collection experience. and according to the current status of the outstanding receivables as of the statement of financial position date

Leasehold rights over land and buildings

The right to lease land and buildings

20 January 1988 A subsidiary company has entered into a sublease agreement of state property with a port and warehouse from a sublessor. The contract has a term of 24 years and the lease term has ended in January 2012. The Company has continued to negotiate the lease of the said assets from the original contract on behalf of the subsidiary. In 2013, the Company received the right to lease directly from the Treasury Department. from the original contract with details and conditions as specified in the new lease dated 26 April 2013. 26 April 2013 The Company has entered into a lease agreement for land and buildings with the Treasury Department. with a lease term of 30 years starting from 22 April 2012 ending 21 April 2042 The company has to pay for the right to lease the land with such buildings on the contract date and other expenses. related to money 32,036,250 baht and must pay the rent annually for the duration of the lease The details of the annual rental rate as stipulated in the contract are as follows:

1 - 5 at an annual rate 1,467,139 baht

6 - 10 at an annual rate 1,687,210 baht

11 - 15 at an annual rate 1,940,290 baht

16 - 20 at an annual rate 2,231,335 baht

21 - 25 at an annual rate 2,566,035 baht

26 - 30 at an annual rate 2,950,940 baht

Total rent for the duration of the contract 64,214,745 baht

Right-of-use assets include leasehold right of land and buildings and vehicle. The leasehold right of land and buildings is leasing the area with the Treasury Department. Such agreement period is 30 years from the years 2012 to 2042.


On August 23, 2018, Treasury Department Samutprakan has issued a letter requesting the Company to pay the rent, rental fees and additional damages in case of building construction and structures without permission, damages from demolition of buildings and structures under the original lease agreement and in case seeking benefits from royal property without permission at the total amount of Baht 222.17 million.


Later on September 12, 2018, the Company has issued a letter of objection to the collection of rent, rental fees and compensation in such amount. The significant reason is the land and buildings lease agreement that is legitimate from the Ministry of Finance. It is carried out according to the resolution of the state property No. 1/2012 as well as informing the rental rate, rental fees and other conditions. The Company has considered and agreed to enter into the lease agreement and always pay the rent and follow the agreement correctly. Therefore, this claim is not in the terms of the agreement. In addition, the various claims for damages are a matter between Ministry of Finance and the lease parties during that time (The Agricultural Co-operative Federation of Thailand). Later, on March 31, 2021 and August 4, 2021, the Company received the letter from the Treasury Office, Samutprakarn for the Company to still pay rent, rental fee and such additional damage by considering to collect Baht 206.46 million (from Baht 222.17 million).


However, on April 26, 2021 and August 26, 2021, the Company made an objection letter for the collection of rental fees and such additional damage and confirmed the compliance under the lease agreement correctly and completely in accordance with the principles or instruction of the Treasury Office District as described above


Later, on March 9, 2023 the Company received a letter from Treasury Office, Samutprakarn for the company to pay the rent, rental fees and damages in case of building demolition and construction without permission sum including interest at 5 percent per annum in total Baht 228.75 million (from previous Baht 206.46 million) within 7 days from the receiving date of the letter. If the above period has passed, the Treasury Office would exercise the right to terminate the lease agreement including confiscate all the pledged security of the lease agreement and will take further legal action.


Later, on March 23, 2023, the Treasury Office, Samutprakarn issued a letter to terminate the lease agreement and confiscated the lease security Baht 1.94 million from the breach of terms from not settling payment within the specified time. Also, it requested the Company to leave the leased premise, deliver the leased property, components and equipment of the leased premise used in operating the business to the Ministry of Finance in a ready state within 30 days from the lease termination date.


On March 29, 2023 the Company made a letter of complaint to seek justice to the Director General of the Treasury Department on the procedures taken by the Treasury Office Samutprakarn that disagree with the agreement provisions and law. The Company did not receive justice and it still confirmed always having complied with the agreement and paying rentals completely in accordance with the agreement requirements.


On February 5, 2024, the Company transferred the land rental payment for the year 2024 in the amount of Baht 1.94 million to the Treasury Office in Samut Prakan. Later, on February 27, 2024, the said office notified the Company of a refund of the rent. The Company received the refund on March 18, 2024. Therefore, on April 3, 2024, the Company placed the said rental money at Samut Prakan Provincial Legal Execution Office to comply with the Crown Property Land Lease Agreement with the Treasury Department. The Company has already notified the Samut Prakan Area Treasury Office on April 9, 2024 . Later, on April 11, 2024 and June 11, 2024 the Company drafted a letter to request a review of the illegal agreement termination.


On November 19, 2024 the Company made a letter to the Ministry of finance regarding the complaint against unjustice practice of the treasury Department, a department under the Ministry of finance, for the Ministry of Finance to consider having the Treasury Department to review and terminate the illegal land lease agreement and on February 6, 2025 the Company made a letter to acknowledge the result of consideration on such matter from the Ministry of Finance. Presently, the Company has not acknowledged the result of such explanation.


As at December 31, 2024, the Company has not recorded the lease, fee and damage following such requirements of the Treasury Department in the financial statements as such matter may require further legal proceeding so there may be uncertainties regarding the payment. Therefore, the Company has not set the reserve from the damage of assets and the allowance for contingent liabilities in the financial statements as at December 31, 2024.

Investment in Marketable Securities

at 31 december 2024 The company has no investments in available-for-sale securities. because the company has no policy to invest money Most of the money will be used as working capital for operations.

Foreign Exchange Risk Management

The company's shipbuilding projects need to import raw materials from abroad, such as Ship Plate, machinery and equipment used in ships The import of such raw materials may be affected by fluctuations in exchange rates, resulting in higher production costs. Therefore, the company has a policy to manage foreign exchange risks that may occur. by purchasing the full amount of foreign currency in advance However Factors that companies use in considering foreign currency purchases to manage their exchange rate risk are:

• There is a large quantity of raw material orders from abroad.

• It takes a long time to process the order or deliver the product.

• The volatility of the money market and the trend of the baht

• Risk prevention cost

Debt Securities with Financial Ratio Requirements

Debt Securities with Financial Ratio Requirements Issued?

No

Factors That May Affect Financial Condition

Factors or Incidents That May Materially Affect Financial Condition

The Thai economy in the fourth quarter of 2024 expanded by 2.5 percent, accelerating from 2.0 percent in the fourth quarter of 2023, with an improvement from the previous year. Supporting factors included an increase in government spending, especially investment spending, continued expansion in private consumption, and an improvement in private investment, continued export growth, as well as a recovery in tourism and related services. In 2024, the number of foreign tourists was 35.56 million.

The Thai shipbuilding and ship repair industry is an industry that is related to many economic sectors, including transportation, tourism, fisheries, and energy exploration and drilling. The growth of these industrial sectors is inextricably linked. In 2024, the Thai economy relied heavily on international trade, accounting for 65.4% of GDP, and more than 83% of imports and exports are primarily transported by sea.

Therefore, developing the potential of Thai shipyards, most of which are smaller than 20,000 DWT, is very important to the Thai economy. This includes strengthening the Thai merchant fleet, promoting tourism capabilities, and increasing fishery production, which will be in line with the Logistics System Development Plan of Thailand 2023-2027 under the 20-Year National Strategy and the 13th National Economic and Social Development Plan.

Adaptation to ESG guidelines for business sustainability: The International Maritime Organization (IMO) has issued measures to reduce greenhouse gas emissions for international shipping by encouraging all ships to use fuel oil with less than 0.5% sulfur, down from 3.5%. It also sets a target to reduce shipping emissions by at least 70% by 2050, including the possible introduction of a carbon tax on cargo ships. This measure will be endorsed by 2025. (The shipping industry generates 2-3% of global carbon emissions.) This has resulted in the shipbuilding and ship repair industry having to adapt in many aspects, such as modifying equipment or adding waste disposal equipment, and designing new environmentally friendly ships.

For the direction of government support for the Thai shipbuilding and ship repair industry, there has been a study and promotion of the development of a master plan under the national strategy, focusing on infrastructure, logistics systems, and digital technology. The transportation infrastructure and logistics system development plan since 2015 has established a special committee to consider standards for promoting the Thai merchant marine. In the report on the consideration of measures to promote the Thai merchant marine, the committee recognized the importance of the water transport sector for the economic growth and stability of Thailand. It studied the operations of the merchant marine in other ASEAN countries, such as Singapore, Malaysia, and Vietnam, as guidelines for developing the Thai merchant marine and gradually pushing for relevant laws under the responsibility of the Harbor Department, Ministry of Transport. The goal of promoting the merchant marine in terms of shipbuilding activities in the short and medium term

Contents